Every satellite needs authorized radio frequencies as well as an orbital slot, and the coordination process for both is slow, international and a real constraint on new systems.

Attention on space congestion focuses on physical crowding, but the scarcer resource is often radio spectrum. A spacecraft that cannot legally transmit is inert regardless of how well it was built.
Frequencies are coordinated internationally
Radio spectrum crosses borders, so its use is coordinated through an international process in which national administrations file on behalf of operators and negotiate with those already using the same bands.
Priority generally follows the order of filing, which creates an incentive to file early and broadly, sometimes well before a system is designed in detail.
Filings carry deadlines by which the system must actually be brought into use, intended to prevent frequencies being reserved indefinitely by projects that never fly.
National regulators add their own layer
An American operator also needs domestic authorization covering transmission, orbital debris mitigation and end-of-life disposal, and those conditions have tightened considerably.
The regulator reviews interference analysis, the proposed orbit and how the spacecraft will be removed when its mission ends, and can impose conditions that change the design.
Earth stations require separate licensing at each site, which is why ground segment approval is a distinct project stream from spacecraft approval.
Interference is the constraint that binds
Two systems using the same frequencies over the same territory will interfere unless they are separated by geography, by pointing angle or by careful power control.
Non-geostationary constellations complicate this because their satellites move, so protection is expressed as limits on the power delivered toward existing users rather than as fixed exclusions.
Meeting those limits shapes antenna design, beam steering and how a constellation schedules which satellite serves a given area.
Bands differ in what they can carry
Lower frequencies penetrate weather and require less precise pointing but offer less bandwidth and are heavily occupied. Higher bands carry far more data and are attenuated by rain.
System designers therefore choose bands based on the service, and the crowding in the most useful bands drives interest in higher frequencies and in optical links between satellites.
Optical crosslinks avoid the coordination problem entirely for satellite-to-satellite traffic, which is one reason they have spread quickly.
Why the paperwork is a gating item
Coordination can take years, longer than building a small satellite, so a project that starts hardware before securing spectrum risks a finished spacecraft with nowhere to transmit.
Access to existing filings has consequently become an asset in its own right, and arrangements to use another party's authorized spectrum are a routine part of how new systems reach service.